Industrial Engineering and Management MCQ PDF

Industrial Engineering and Management MCQ PDF

Read More Mechanical Engineering Objective Questions


1. Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time.

A. One-fourth

B. One-half

C. Equal to

D. Twice

Answer: Option B

Solution:

Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is One-half the standard time.

Read More Mechanical Engineering Questions and Answers


2. Critical Path Net Work helps an engineer

A. To concentrate his attention on critical activities

B. To divert the resources from noncritical advanced activities to critical activities

C. To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project

D. All of the above

Answer: Option D

Solution:

Critical Path Net Work helps an engineer

- To concentrate his attention on critical activities

- To divert the resources from noncritical advanced activities to critical activities

- To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project

Read More Mechanical Objective Questions

Industrial Engineering and Management MCQ PDF



3. Queueing theory is used for

A. Inventory problems

B. Traffic congestion studies

C. Job-shop scheduling

D. All of the above

Answer: Option D

Solution:

Queueing theory is used for

- Inventory problems

- Traffic congestion studies

- Job-shop scheduling

Read More Basic Mechanical Engineering MCQ


4. Percent idle time for men or machines is found by

A. Work sampling

B. Time study

C. Method study

D. Work study

Answer: Option A

Solution:

Percent idle time for men or machines is found by work sampling.

Read More Mechanical Engineering MCQs


5. A critical activity has

A. Maximum slack

B. Minimum slack

C. Zero slack

D. Average slack

Answer: Option C

Solution:

A critical activity has Zero slack

Read More Mechanical Objective Questions



6. The critical activity has

A. Maximum float

B. Minimum float

C. Zero float

D. Average float

Answer: Option C

Solution:

The critical activity has Zero float

Read More Mechanical Engineering Questions and Answers


7. In order that linear programming techniques provide valid results

A. Relations between factors must be linear (positive)

B. Relations between factors must be linear (negative)

C. Either (A) or (B)

D. Only one factor should change at a time, others remaining constant

Answer: Option C

Solution:

In order that linear programming techniques provide valid results

- Relations between factors must be linear (positive)

- Relations between factors must be linear (negative)

Read More Mechanical Objective Questions



8. Standard time is defined as

A. Normal time + allowances

B. Normal time + idle time + allowances

C. Normal time + idle time

D. Only normal time for an operation

Answer: Option A

Solution:

Standard time is defined as Normal time + allowances

Read More Basic Mechanical Engineering MCQ


9. In a PERT chart

A. All activities should be numbered

B. Only important activities should be numbered

C. Only critical activities are numbered

D. Only selected activities are numbered

Answer: Option A

Solution:

In a PERT chart All activities should be numbered

Answer & Solution

Read More Mechanical Engineering MCQs


10. Slack of various events on the critical path in PERT/CPM chart

A. Increases continuously

B. Decreases continuously

C. Remain constant

D. May increase or decrease depending on various factors

Answer: Option C

Solution:

Slack of various events on the critical path in PERT/CPM chart Remain constant

Read More Mechanical Engineering Questions and Answers

Industrial Engineering and Management MCQ PDF


11. In process layout

A. Handling and backtracking of materials is too much

B. Production control is more difficult and costly

C. Routing and scheduling is more difficult

D. All of the above

Answer: Option D

Solution:

In process layout

- Handling and backtracking of materials is too much

- Production control is more difficult and costly

- Routing and scheduling is more difficult

Read More Mechanical Objective Questions


12. In product layout

A. Specialized and strict supervision is required

B. Machines can not be used to their maximum capacity

C. Manufacturing cost rises with a fall in the volume of production

D. All of the above

Answer: Option D

Solution:

In product layout

- Specialized and strict supervision is required

- Machines can not be used to their maximum capacity

- Manufacturing cost rises with a fall in the volume of production

Read More Mechanical Objective Questions

Industrial Engineering and Management MCQ PDF


13. A low unit cost can be obtained by following

A. Product layout

B. Functional layout

C. Automatic material handling equipment

D. Specialization of operation

Answer: Option A

Solution:

A low unit cost can be obtained by product layout.

Read More Basic Mechanical Engineering MCQ


14. Gantt chart gives information about

A. Scheduling and routing

B. Sales

C. Production schedule

D. Machine utilization

Answer: Option C

Solution:

Frequently used in project management, a Gantt chart provides a graphical illustration of a schedule that helps

to plan, coordinate, and track specific tasks in a project.

Read More Mechanical Engineering MCQs


15. Gantt charts provide information about

A. Break-even point analysis

B. Production schedule

C. Material handling layout

D. Determining selling price

Answer: Option B

Solution:

Frequently used in project management, a Gantt chart provides a graphical illustration of a schedule that helps to plan, coordinate, and track specific tasks in a project.

Read More Mechanical Objective Questions


16. Scheduling gives information about

A. When work should start and how much work should be completed during a certain period

B. When work should complete

C. That how idle time can be minimized

D. Proper utilization of machines

Answer: Option A

Solution:

Scheduling gives information about When work should start and how much work should be completed during a certain period

Read More Mechanical Engineering Questions and Answers


17. In PERT analysis, critical path is obtained by joining events having

A. +ve slack

B. -ve slack

C. Zero slack

D. Dummy activities

Answer: Option C

Solution:

In PERT analysis, critical path is obtained by joining events having Zero slack

Read More Mechanical Engineering MCQs


18. CPM has following time estimate

A. One time estimate

B. Two time estimate

C. Three time estimate

D. Four time estimate

Answer: Option A

Solution:

CPM has one time estimate

Read More Basic Mechanical Engineering MCQ


19. PERT has following time estimate

A. One time estimate

B. Two time estimate

C. Three time estimate

D. Four time estimate

Answer: Option C

Solution:

PERT has three time estimate

Read More Mechanical Objective Questions


20. The routing function in a production system design is concerned with

A. Manpower utilization

B. Quality assurance of the product

C. Machine utilization

D. Optimizing material flow through the plant

Answer: Option C

Solution:

The routing function in a production system design is concerned with Machine utilization

Read More Mechanical Engineering Objective Questions


Industrial Engineering and Management MCQ PDF


21. The two bin system is concerned with

A. Ordering procedure

B. Forecasting sales

C. Production planning

D. Despatching and expediting

Answer: Option A

Solution:

The two bin system is concerned with ordering procedure.

Read More Mechanical Engineering Questions and Answers


22. Work study is concerned with

A. Improving present method and finding standard time

B. Motivation of workers

C. Improving production capability

D. Improving production planning and control

Answer: Option A

Solution:

Work study is concerned with improving present method and finding standard time.

Read More Mechanical Engineering MCQs


23. Activity slack or float of any event on a PERT/CPM chart is represented by

A. Latest start time of succeeding event earliest finish time of preceding event activity time

B. Latest start time of the event earliest start time of the event

C. Latest finish time of event earliest finish time of the event

D. Anyone of the above

Answer: Option D

Solution:

Activity slack or float of any event on a PERT/CPM chart is represented by

- Latest start time of succeeding event earliest finish time of preceding event activity time

- Latest start time of the event earliest start time of the event

- Latest finish time of event earliest finish time of the event

Read More Basic Mechanical Engineering MCQ


24. Acceptance sampling is widely used in

A. Batch production

B. Job production

C. Mass production

D. All of the above

Answer: Option C

Solution:

Acceptance sampling is widely used in Mass production

Read More Mechanical Engineering MCQs


25. Dummy activities are used to

A. Determine the critical path

B. Determine the project completion time

C. Maintain the required net work

D. None of these

Answer: Option C

Solution:

Dummy activities are used to Maintain the required net work

Read More Mechanical Objective Questions


26. The time which results in the least possible direct cost of an activity is known as

A. Normal time

B. Slow time

C. Crash time

D. Standard time

Answer: Option B

Solution:

The time which results in the least possible direct cost of an activity is known as slow time

Read More Mechanical Engineering Questions and Answers



27. When slack of an activity is negative

A. It represents a situation where extra resources are available and the completion of project is not delayed

B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time

C. The activity is critical and any delay in its performance will delay the completion of whole project

D. All of the above

Answer: Option B

Solution:

When slack of an activity is negative It represents that a programme falls behind schedule and additional resources are required to complete the project in time

Read More Mechanical Objective Questions


28. When slack of an activity is positive

A. It represents a situation where extra resources are available and the completion of project is not delayed

B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time

C. The activity is critical and any delay in its performance will delay the completion of whole project

D. Any one of the above

Answer: Option A

Solution:

When slack of an activity is positive - it represents a situation where extra resources are available and the completion of the project is not delayed.

When slack of an activity is negative - it represents that a program falls behind schedule and additional resources are required to complete the project in time.

When slack of an activity is zero - the activity is critical and any delay in its performance will delay the completion of the whole project.

Read More Basic Mechanical Engineering MCQ


29. If TL is the largest allowable event occurrence time, total activity slack (s) is equal to

A. Latest start time earliest start time

B. Latest finish time earliest finish time (EFT)

C. TLEFT

D. All of the above

Answer: Option D

Solution:

If TL is the largest allowable event occurrence time, total activity slack (s) is equal to

- Latest start time earliest start time

- Latest finish time earliest finish time (EFT)

- TLEFT

Read More Mechanical Engineering MCQs


30. Tick the odd man out

A. Taylor

B. Drucker

C. McGregor

D. Galileo

Answer: Option D

Solution:

Galileo discovered telescope, but also a series of devices that would have a profound impact on surveying, the use of artillery, the development of clocks, and meteorology

Read More Mechanical Engineering Questions and Answers

Industrial Engineering and Management MCQ PDF


What is industrial engineering and production management?

Industrial engineering and production management are two related fields that focus on optimizing and improving industrial and manufacturing processes. Industrial engineering is a branch of engineering that deals with the design, improvement, and implementation of integrated systems of people, materials, equipment, and energy. It combines the principles of mathematics, physics, and social sciences to optimize complex systems. Industrial engineers are concerned with increasing efficiency, reducing costs, and improving the quality of products and services. Production management, on the other hand, is the process of planning, organizing, directing, and controlling the production process in order to achieve the desired goals. It involves managing the resources required for production, such as materials, labor, and equipment, and making sure that everything is running smoothly and efficiently. The goal of production management is to produce high-quality products in a cost-effective manner. Both industrial engineering and production management are concerned with improving the performance of manufacturing processes, but they approach the problem from different angles. Industrial engineering focuses on the design and optimization of the manufacturing system, while production management focuses on the day-to-day management of the production process. Together, these two fields play a critical role in modern manufacturing and help companies to increase productivity, reduce costs, and improve the quality of their products.

Read More Basic Mechanical Engineering MCQ

Read More MCQ for Diploma Mechanical Engineering

Read More Mechanical Engineering Questions and Answers

Read More Mechanical Engineering MCQs

Read More Mechanical Objective Questions

Read More Mechanical Engineering Objective Questions


Which website is best for MCQ exam?




Which is the best MCQ sites for competitive exams?

mcqquestions.net - This website offers a large collection of multiple-choice questions across a range of subjects and topics, including general knowledge, current affairs, aptitude, and more. The site is free to use, and users can access questions by topic or by exam.


Which is the best GK website for competitive exams?

mcqquestions.net - This website offers a large collection of multiple-choice questions best GK website for competitive exams.

Post a Comment

0 Comments