Industrial Engineering and Management MCQ PDF
Read More Mechanical Engineering Objective Questions
1. Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time.
A. One-fourth
B. One-half
C. Equal to
D. Twice
Answer: Option B
Solution:
Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is One-half the standard time.
Read More Mechanical Engineering Questions and Answers
2. Critical Path Net Work helps an engineer
A. To concentrate his attention on critical activities
B. To divert the resources from noncritical advanced activities to critical activities
C. To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
D. All of the above
Answer: Option D
Solution:
Critical Path Net Work helps an engineer
- To concentrate his attention on critical activities
- To divert the resources from noncritical advanced activities to critical activities
- To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
Read More Mechanical Objective Questions
3. Queueing theory is used for
A. Inventory problems
B. Traffic congestion studies
C. Job-shop scheduling
D. All of the above
Answer: Option D
Solution:
Queueing theory is used for
- Inventory problems
- Traffic congestion studies
- Job-shop scheduling
Read More Basic Mechanical Engineering MCQ
4. Percent idle time for men or machines is found by
A. Work sampling
B. Time study
C. Method study
D. Work study
Answer: Option A
Solution:
Percent idle time for men or machines is found by work sampling.
Read More Mechanical Engineering MCQs
5. A critical activity has
A. Maximum slack
B. Minimum slack
C. Zero slack
D. Average slack
Answer: Option C
Solution:
A critical activity has Zero slack
Read More Mechanical Objective Questions
6. The critical activity has
A. Maximum float
B. Minimum float
C. Zero float
D. Average float
Answer: Option C
Solution:
The critical activity has Zero float
Read More Mechanical Engineering Questions and Answers
7. In order that linear programming techniques provide valid results
A. Relations between factors must be linear (positive)
B. Relations between factors must be linear (negative)
C. Either (A) or (B)
D. Only one factor should change at a time, others remaining constant
Answer: Option C
Solution:
In order that linear programming techniques provide valid results
- Relations between factors must be linear (positive)
- Relations between factors must be linear (negative)
Read More Mechanical Objective Questions
8. Standard time is defined as
A. Normal time + allowances
B. Normal time + idle time + allowances
C. Normal time + idle time
D. Only normal time for an operation
Answer: Option A
Solution:
Standard time is defined as Normal time + allowances
Read More Basic Mechanical Engineering MCQ
9. In a PERT chart
A. All activities should be numbered
B. Only important activities should be numbered
C. Only critical activities are numbered
D. Only selected activities are numbered
Answer: Option A
Solution:
In a PERT chart All activities should be numbered
Answer & Solution
Read More Mechanical Engineering MCQs
10. Slack of various events on the critical path in PERT/CPM chart
A. Increases continuously
B. Decreases continuously
C. Remain constant
D. May increase or decrease depending on various factors
Answer: Option C
Solution:
Slack of various events on the critical path in PERT/CPM chart Remain constant
Read More Mechanical Engineering Questions and Answers
Industrial Engineering and Management MCQ PDF
11. In process layout
A. Handling and backtracking of materials is too much
B. Production control is more difficult and costly
C. Routing and scheduling is more difficult
D. All of the above
Answer: Option D
Solution:
In process layout
- Handling and backtracking of materials is too much
- Production control is more difficult and costly
- Routing and scheduling is more difficult
Read More Mechanical Objective Questions
12. In product layout
A. Specialized and strict supervision is required
B. Machines can not be used to their maximum capacity
C. Manufacturing cost rises with a fall in the volume of production
D. All of the above
Answer: Option D
Solution:
In product layout
- Specialized and strict supervision is required
- Machines can not be used to their maximum capacity
- Manufacturing cost rises with a fall in the volume of production
Read More Mechanical Objective Questions
13. A low unit cost can be obtained by following
A. Product layout
B. Functional layout
C. Automatic material handling equipment
D. Specialization of operation
Answer: Option A
Solution:
A low unit cost can be obtained by product layout.
Read More Basic Mechanical Engineering MCQ
14. Gantt chart gives information about
A. Scheduling and routing
B. Sales
C. Production schedule
D. Machine utilization
Answer: Option C
Solution:
Frequently used in project management, a Gantt chart provides a graphical illustration of a schedule that helps
to plan, coordinate, and track specific tasks in a project.
Read More Mechanical Engineering MCQs
15. Gantt charts provide information about
A. Break-even point analysis
B. Production schedule
C. Material handling layout
D. Determining selling price
Answer: Option B
Solution:
Frequently used in project management, a Gantt chart provides a graphical illustration of a schedule that helps to plan, coordinate, and track specific tasks in a project.
Read More Mechanical Objective Questions
16. Scheduling gives information about
A. When work should start and how much work should be completed during a certain period
B. When work should complete
C. That how idle time can be minimized
D. Proper utilization of machines
Answer: Option A
Solution:
Scheduling gives information about When work should start and how much work should be completed during a certain period
Read More Mechanical Engineering Questions and Answers
17. In PERT analysis, critical path is obtained by joining events having
A. +ve slack
B. -ve slack
C. Zero slack
D. Dummy activities
Answer: Option C
Solution:
In PERT analysis, critical path is obtained by joining events having Zero slack
Read More Mechanical Engineering MCQs
18. CPM has following time estimate
A. One time estimate
B. Two time estimate
C. Three time estimate
D. Four time estimate
Answer: Option A
Solution:
CPM has one time estimate
Read More Basic Mechanical Engineering MCQ
19. PERT has following time estimate
A. One time estimate
B. Two time estimate
C. Three time estimate
D. Four time estimate
Answer: Option C
Solution:
PERT has three time estimate
Read More Mechanical Objective Questions
20. The routing function in a production system design is concerned with
A. Manpower utilization
B. Quality assurance of the product
C. Machine utilization
D. Optimizing material flow through the plant
Answer: Option C
Solution:
The routing function in a production system design is concerned with Machine utilization
Read More Mechanical Engineering Objective Questions
Industrial Engineering and Management MCQ PDF
21. The two bin system is concerned with
A. Ordering procedure
B. Forecasting sales
C. Production planning
D. Despatching and expediting
Answer: Option A
Solution:
The two bin system is concerned with ordering procedure.
Read More Mechanical Engineering Questions and Answers
22. Work study is concerned with
A. Improving present method and finding standard time
B. Motivation of workers
C. Improving production capability
D. Improving production planning and control
Answer: Option A
Solution:
Work study is concerned with improving present method and finding standard time.
Read More Mechanical Engineering MCQs
23. Activity slack or float of any event on a PERT/CPM chart is represented by
A. Latest start time of succeeding event earliest finish time of preceding event activity time
B. Latest start time of the event earliest start time of the event
C. Latest finish time of event earliest finish time of the event
D. Anyone of the above
Answer: Option D
Solution:
Activity slack or float of any event on a PERT/CPM chart is represented by
- Latest start time of succeeding event earliest finish time of preceding event activity time
- Latest start time of the event earliest start time of the event
- Latest finish time of event earliest finish time of the event
Read More Basic Mechanical Engineering MCQ
24. Acceptance sampling is widely used in
A. Batch production
B. Job production
C. Mass production
D. All of the above
Answer: Option C
Solution:
Acceptance sampling is widely used in Mass production
Read More Mechanical Engineering MCQs
25. Dummy activities are used to
A. Determine the critical path
B. Determine the project completion time
C. Maintain the required net work
D. None of these
Answer: Option C
Solution:
Dummy activities are used to Maintain the required net work
Read More Mechanical Objective Questions
26. The time which results in the least possible direct cost of an activity is known as
A. Normal time
B. Slow time
C. Crash time
D. Standard time
Answer: Option B
Solution:
The time which results in the least possible direct cost of an activity is known as slow time
Read More Mechanical Engineering Questions and Answers
27. When slack of an activity is negative
A. It represents a situation where extra resources are available and the completion of project is not delayed
B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time
C. The activity is critical and any delay in its performance will delay the completion of whole project
D. All of the above
Answer: Option B
Solution:
When slack of an activity is negative It represents that a programme falls behind schedule and additional resources are required to complete the project in time
Read More Mechanical Objective Questions
28. When slack of an activity is positive
A. It represents a situation where extra resources are available and the completion of project is not delayed
B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time
C. The activity is critical and any delay in its performance will delay the completion of whole project
D. Any one of the above
Answer: Option A
Solution:
When slack of an activity is positive - it represents a situation where extra resources are available and the completion of the project is not delayed.
When slack of an activity is negative - it represents that a program falls behind schedule and additional resources are required to complete the project in time.
When slack of an activity is zero - the activity is critical and any delay in its performance will delay the completion of the whole project.
Read More Basic Mechanical Engineering MCQ
29. If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
A. Latest start time earliest start time
B. Latest finish time earliest finish time (EFT)
C. TLEFT
D. All of the above
Answer: Option D
Solution:
If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
- Latest start time earliest start time
- Latest finish time earliest finish time (EFT)
- TLEFT
Read More Mechanical Engineering MCQs
30. Tick the odd man out
A. Taylor
B. Drucker
C. McGregor
D. Galileo
Answer: Option D
Solution:
Galileo discovered telescope, but also a series of devices that would have a profound impact on surveying, the use of artillery, the development of clocks, and meteorology
Read More Mechanical Engineering Questions and Answers
Industrial Engineering and Management MCQ PDF
What is industrial engineering and production management?
Industrial engineering and production management are two related fields that focus on optimizing and improving industrial and manufacturing processes. Industrial engineering is a branch of engineering that deals with the design, improvement, and implementation of integrated systems of people, materials, equipment, and energy. It combines the principles of mathematics, physics, and social sciences to optimize complex systems. Industrial engineers are concerned with increasing efficiency, reducing costs, and improving the quality of products and services. Production management, on the other hand, is the process of planning, organizing, directing, and controlling the production process in order to achieve the desired goals. It involves managing the resources required for production, such as materials, labor, and equipment, and making sure that everything is running smoothly and efficiently. The goal of production management is to produce high-quality products in a cost-effective manner. Both industrial engineering and production management are concerned with improving the performance of manufacturing processes, but they approach the problem from different angles. Industrial engineering focuses on the design and optimization of the manufacturing system, while production management focuses on the day-to-day management of the production process. Together, these two fields play a critical role in modern manufacturing and help companies to increase productivity, reduce costs, and improve the quality of their products.
Read More Basic Mechanical Engineering MCQ
Read More MCQ for Diploma Mechanical Engineering
Read More Mechanical Engineering Questions and Answers
Read More Mechanical Engineering MCQs
Read More Mechanical Objective Questions
Read More Mechanical Engineering Objective Questions